700 East from 400 South to Pages Lane. 800 East between 600 South and 800 South. 600 South, 650 South, 700 South, 800 South & 950 South East of 700 East.
K Krammer
4/25/2019 08:10:04 pm
Estimated time to complete repair would be helpful.
Robert
4/27/2019 01:23:58 pm
A Excavation Contractor has been hired. They have submitted Blue Stakes and intend to start on the 700 East mainline break on Monday April 29th. Then they will move to the service line leaks on 700 South and 800 South near 800 East. If repairs proceed well everything but 700 South and 800 South East of 700 East will be in service on Monday night. 700 South and 800 South East of 700 East should be in service by Wednesday night. Comments are closed.
|
For specific comments or questions please contact us.